Month: August 2017

Vintage Gyprock

During the plastering process, we have decided to strip the original P&S lounge/dining room. It’s about 34sqm and needs to flow through to the new section. It’s got new doors and the opening to the new section but now it needs the timber flooring which […]

Leave a comment

Progress Photos Feb 2017 +

I’ve rounded up the best photos that show our progress since February 2017 onwards. You can check out the first stage of Progress Photos for 2016 here. February 2017, the pool deck area is ready for glass fencing..a massive job which we are doing with […]

Leave a comment

Travel for work and soul

In March we are often required to travel for trade shows, so our scheduled pool completion was once again on hold as we wouldn’t be there to see it happen. April and June was filled with kitchen and bathroom specifying, so lots to keep us […]

Leave a comment

Decision making

By March we had reached the 12 month mark of our project, although not all of that time has been spent building. Between August 2016 rains, a lot of excavation for the pool and drainage, Christmas break and so on…we probably had only done about […]

Leave a comment

Rain, rain go away

It’s been a few months since my last post, which is pretty lame. February in fact…! I cannot believe how or where the time has gone. But we have made significant progress. So, I’ll be trying to post a bunch of articles to catch up. […]

Leave a comment